• 003
  • 001
  • 002
  • 004

BEREZOVSKAYA 800 MW COAL FIRED POWER PLANT PROJECT

CLIENT

E.ON Russia

SCOPE OF WORK

Mechanical Erection Works

SECTOR

Power Plants

LOCATION

Sharypovo, Krasnoyarsk Region, the Russian Federation

PROJECT DURATION

June 2012 – September 2015

Project Description

ENKA was awarded the contract for the boiler’s mechanical erection work at the Berezovskaya Coal Fired Power Plant located at Sharypovo, Krasnoyarsk Region of the Russian Federation in June 2012.

Berezovskaya Coal Fired Power Plant Project consisted of construction of the 3rd power block with the capacity of 800 MW to increase the overall plant capacity to 2,400 MW.

Unique Challenges

Majority of the erection works at the Berezovskaya Power Plant Project were carried on inside a 72m x 81m x 117m (height) enclosed building right next to two operating coal fired units. Inevitably; i) the works were executed at extreme heights causing safety hazards and, ii) coal dust from operating blocks was present at the work places, that endanger health of the workers. ENKA overcame these hazards by prioritizing HSE in mutual cooperation with the Owner. Another challenge faced due to working inside an enclosed building was that the work fronts were limited due to specific erection sequences which also brought about interfaces between crews executing different lines of works. ENKA was able to manage this by proper planning of the works. Further, even though the erection was being done inside a closed building, the erection sequence and the erection methods governed that in order to minimize the number of lifts (circa 2000 ea with weight of lifted blocks differing from 50 kg to 185 tons), the elements were to be preassembled to blocks of maximum liftable weights and sizes. Hence the preassembly works were mainly executed outdoors, which required ENKA to use its vast winterization experience.

ENKA Scope of Services

ENKA’s scope as the mechanical erection works contractor for the construction of the Berezovskaya Coal Fired Power Plant Project consisted of pre-installation preparatory works, assembly works (enlarged assembly of the parts of the boiler and auxiliary equipment), installation works, preassembly of wall modules (boiler pressure parts), field welding joints touch-up painting works, hydraulic testing of the boiler.

Significant Features and Accomplishments

  • 9.24 million work-hours without Lost Time Incident
  • Construction of the third power block of 800 MW capacity resumed after 20 years of a halt due to the collapse of the Soviet Union
  • Plant capacity increased to 2,400 MW
  • Berezovskaya Power Plant is the only power plant in Russia with 800 MW power units where coal is used as fuel, all the rest of the heat power plants with same power units are operated using gas
  • Being fed with brown coal from the open pit mine that is 14 km away, Berezovskaya Power Plant is vital for development of the Eastern Siberia’s power industry

Key Quantities

Structural Steel 5,177 tons
Mech. Equipment 3,629 tons
Ductwork 3,784 tons
A/G Piping 3,074 tons
Pressure Parts 4,119 tons

Gallery