• 001
  • 002
  • 003

BURSA NATURAL GAS COMBINED CYCLE POWER PLANT

CLIENT

Turkish Electricity Generation & Transmission Co. Inc. – TEAŞ

CONTRACTOR

ENKA – MITSUBISHI – ITOCHU Consortium

SECTOR

Power Plants

LOCATION

Bursa, Türkiye

CONTRACT TYPE / SCOPE OF WORK

Lump Sum Turn Key / Turn-key Engineering, Procurement, Construction, Commissioning & Start-up

PROJECT DURATION

May 1996 – June 1999

Project Description

The Japanese-Turkish consortium of MHI-ENKA-MC-ITC was awarded the contract to build a 1,400 MW natural gas fired combined cycle power plant in Bursa on a turn-key basis following a tender by TEAŞ in 1995. Using the latest technology, the Bursa Power Plant stood out as the largest and most efficient power plant of its period in Türkiye.

The project encompassed all civil works, sub and superstructures, and supply of auxiliary components. The scope of works also included the supply, installation, testing and putting into operation of the mechanical and electrical systems at the power plant. The main components were supplied from Japan by MHI. The project was financed by Japanese EXIM and a number of commercial banks.

The main plant consists of two power blocks. Each has a set of two combustion turbines/generators, two heat recovery steam generators, one steam turbine/generator and one closed cooling water system with a 135 m natural draft dry cooling tower.

The total net output of the combined cycle power plant is 1,409 MW, which is achieved by four gas turbines/generators each with a nominal capacity of 239 MW and two steam turbines/generators each with a nominal capacity of 238 MW. The annual power generation capacity of the plant is 10 billion kWh.

ENKA Scope of Services

The project is the largest of its kind in the world. Includes design and engineering, equipment supply, construction, erection, commissioning and putting into operation of the Natural Gas Fired Combined Cycle Power Plant on a turn-key basis. The main plant consists of 4 Gas Turbines (each 240 MW), 4 sets Heat Recovery Steam Generators and 2 Steam Turbines (each 237,5 MW) Main items of work and services are complete design and engineering of the plant and auxiliaries, complete civil works for buildings and structures, including steel structure fabrication and erection, infrastructural works, mechanical and electrical supply and erection works including installation of Gas Turbo­ Generator sets, Heat Recovery Steam Generators, Steam Turbo – Generator sets, Cooling Water System incorporating 2 pieces of reinforced concrete natural draft dry Cooling Towers (135 m high, 120 m base diameter), Water Treatment Plant, 154 kV and 380 kV Switchyards, Central Control Building, Service and Auxiliary Buildings . The project also includes construction of the main access road to plant and the social and administrative buildings for TEAŞ.

Key Quantities

Earthworks 1,250,000 m³
Concrete 92,000 m³
Formwork 255,000 m²
Reinforcing Steel 7,500 tons
Structural Steel 8,000 tons
Mech. Equipment 42,500 tons
Insulation & Paint 49,500 m²

Gallery