ENKA was awarded several contracts, beginning in 1998, for the development of the Kashagan Oil Field in Kazakhstan; the largest oil field discovered in the country for the last 30 years.
Initial construction contracts included the Bautino Supply Base in 1998, miscellaneous civil and quarrying contracts between 1999 and 2001 and the Offshore Civil Works Contract between 2001 and 2004.
Additionally, in 2005, ENKA signed another contract with the operator of the giant Kashagan Oil Field, to build berms, islands and other offshore structures required for the Kashagan Oil Field development. Fill materials for the work are quarried and hauled 180 nautical miles to the Kashagan Oil Field from Bautino village, where the contractor’s job-site base is located. The amount of fill material hauled offshore by a fleet of 64 vessels at the peak, has already exceeded 10 million tons over the first six years of the contract.
In addition to the main development works on Kashagan Oil Field, ENKA was awarded two further contracts for the Pipeline Replacement Project, which started in 2015 and completed in 2016. These contracts included the extension of the available Riser Island of the two main facilities and the dredging and trenching activities for pipeline laying around the islands.
Apart from reducing the construction season to 7.5 months a year, the severe winter climate conditions of the Northern Caspian Sea necessitated the protection of the constructed offshore structures against surging ice by the building of rigid ice barriers.
The special techniques needed for the construction of the offshore structures, include the use of GPS equipment mounted on excavators that, with custom-made software, carried out the profiling and grading work underwater. These were conducted with an extremely high degree of accuracy, for the underwater berms required for the drilling rig.
In 2016, ENKA was awarded a contract for the Early Works, Site Preparation, Load-in, Installation, Hook-up, Mechanical Completion, Pre-Commissioning and Commissioning of Topsides for EPC-3 Island located in the Kashagan Oil Field. The project was completed early 2017 and EPC-3 Island has been producing oil and gas since February 2017 via main production and processing Complex, D-Island, which is also known as Hub-1.
Also, ENKA undertook the Cargo Transportation Route Channel Dredging Work and Marine Installation Work for Prorva Access Channel between 2017-2018. The Cargo Transportation Route Channel Project serves as a route for transporting pre-fabricated pipe rack modules for use in the construction works of the Future Growth Project.
Currently, ENKA is providing Marine Operations Services and Vessel/Equipment Rental.