• 01

KAZAN 250 MW COMBINED CYCLE POWER PLANT

CLIENT

PJSC Kazanorgsintez (Member of the TAIF Group)

SCOPE OF WORK

Engineering, Procurement, Construction, Start-Up and Commissioning

SECTOR

Power Plants

LOCATION

Kazan, Russian Federation

PROJECT DURATION

August 2023 – December 2025

Project Description

ENKA and Siemens Energy had formed a consortium for the implementation of 250 MW Combined Cycle Power Plant in Kazan in the Republic of Tatarstan, the Russian Federation for PJSC Kazanorgsintez, a member of the SIBUR Holding PJSC. The contract was signed between Siemens Energy and the client on October 2nd, 2019 for the delivery, installation and commissioning of one SGT5-2000E gas turbine, one SST-600 steam turbine, one heat recovery steam generator and all associated systems.

The plant will be capable of using natural gas as the primary fuel and the associated gas derivatives (syngas) that are by-products of PJSC Kazanorgsintez’s production processes. The project consists of 4 divisions:

› Combined cycle gas turbine, main construction area,

› Linear facility; utility and gas pipelines (5 pipelines up to 3.5 km),

› Gas mixing station and 2 gas pipelines in the territory of the client’s existing facility,

 › Connection to switchyard and electricity distribution works (in the Siemens Energy’s scope).

ENKA Scope of Services

Within the framework of this “Cooperation Agreement” ENKA is to perform the engineering, procurement and construction (EPC) works. ENKA will also be responsible for commissioning. Siemens will supply the gas and steam turbines.

Key Quantities

Backfill 97,000 m3
Concrete 19,000 m3
Formwork 29,000 m2
Rebar 2,010 t
Steel Structure 3,502 t
Cladding 23,250 m2
Large Bore Piping 1,605 t
Small Bore Piping 22 t

Gallery