ENKA and Siemens Energy had formed a consortium for the implementation of 250 MW Combined Cycle Power Plant in Kazan in the Republic of Tatarstan, the Russian Federation for PJSC Kazanorgsintez, a member of the SIBUR Holding PJSC. The contract was signed between Siemens Energy and the client on October 2nd, 2019 for the delivery, installation and commissioning of one SGT5-2000E gas turbine, one SST-600 steam turbine, one heat recovery steam generator and all associated systems.
The plant will be capable of using natural gas as the primary fuel and the associated gas derivatives (syngas) that are by-products of PJSC Kazanorgsintez’s production processes. The project consists of 4 divisions:
› Combined cycle gas turbine, main construction area,
› Linear facility; utility and gas pipelines (5 pipelines up to 3.5 km),
› Gas mixing station and 2 gas pipelines in the territory of the client’s existing facility,
› Connection to switchyard and electricity distribution works (in the Siemens Energy’s scope).