• 001
  • 002
  • 003

RIJNMOND ENERGY CENTER

CLIENT

Rijnmond Energie CV

CONTRACTOR

BECHTEL – ENKA HOLLAND VoF Joint Venture (ENKA’s share 35 %)

SECTOR

Power Plants

LOCATION

Rotterdam, The Netherlands

CONTRACT TYPE / SCOPE OF WORK

Lump Sum Turn Key / Engineering, Procurement, Construction, Commissioning

PROJECT DURATION

August 2002 – June 2004

Project Description

In 2002, ENKA-Bechtel Joint Venture was awarded the Lump Sum Turnkey EPC contract for the Rijnmond Energy Center Project, a combined cycle cogeneration power plant in the Netherlands.

The project was the first independent power plant in northwest Europe since the 1996 European Union Electricity Directive.

The Rijnmond Energy Center was a natural gas fueled facility with a nominal 790 MW net output. It consisted of two combustion turbine generators (CTGs), two fired heat-recovery steam generators (HRSGs), and one lateral exhaust steam turbine generator (STG) in a 2x2x1 configuration. Plant cooling was provided by a mechanical draft, plume-abated cooling tower, with makeup water from the nearby Petroleum Haven, following processing through an acti-floc clarifier.

The plant was designed to deliver 125 tons/hour of steam to the nearby Shell refinery and was designed to a capacity of exporting up to 350 tons/hour.

The CTGs were delivered by Siemens (Germany), the heat recovery steam generators by SFL (the Netherlands), the STG was by Alstom Power (Germany), the DCS control systems were by ABB-Bailey (USA), the water treatment plant was by US Filter (USA), the main and auxiliary transformers by Areva (Türkiye), the switchyard by Siemens (Türkiye) and the cooling towers by Balcke-Dür (Germany).

Construction of the Rijnmond Energy Center commenced in August, 2002. Substantial completion was achieved within 22 months in June, 2004, five months ahead of schedule.

ENKA Scope of Services

ENKA-Bechtel Joint Venture’s scope as the EPC contractor of the Rijnmond Combined Cycle Power Plant Project covered all the works including design, engineering, equipment supply, construction and commissioning works of 790 MW Natural Gas Combined Cycle Cogeneration Power Plant consisting of a 2x2x1 combined cycle arrangement. ENKA workforce reached to 860 employees during the peak periods of the project. ENKA further provided training for the O&M personnel for operation and maintenance of the plant.

Key Quantities

Earthworks 146,449 m³
Concrete 17,382 m³
Structural Steel 2,381 tons
A/G Piping 12,955 tons
Cabling 287,165 lm
Insulation & Paint 6,251 m²
Buildings 2,774 m²

Gallery