Currently, over 3,500 employees are working with a superior effort for a wide range of works. 20.5 million m3 of excavation, 7.8 million m3 of fill and 259,000 m3 of concreting works have been completed.
In the Sector 1, the majority of earthworks have been completed, drainage, paving and finishing works are in progress. Piling, foundations, elevations, beam installation and deck construction works are advancing at a rapid pace by the structure team. Laying of subbase in main alignment has started.
In the Sector 2, excavation and fill works, embankment scour protection works and piling, foundation and elevation works for bridges are progressing contemporaneously. Preparations of precast girders are also ongoing while the installation of them is expected to start shortly.
In the Sector 3, beam installations have started. Excavation and fill works, embankment scour protection works and piling, foundation and elevation works for bridges are still progressing. In addition, Adrani (second) camp is partially opened and the construction is expected to finish soon.
A total of 7 million person-hours and 309 days had been worked without any lost time incident (LTI) on the project.