The Corridors 8 & 10d Motorway Project in North Macedonia is progressing through the joint efforts of ENKA and Bechtel. More than 2,000 people, including subcontractors, are actively working across various project areas.
In Sections 1,2 and 4, earthworks and construction of structures are advancing and drainage works are also ongoing. As of the end of June 2025, a total of 2.8 million m³ of excavation, 530,000 m³ of fill, 390,000 tonnes of aggregate production and 38,000 m³ of concrete works have been completed.
In Section 1, approximately 95% of the accommodation camp construction has been completed, with a total active capacity reaching 1,104 people. In Section 4, significant progress has been made in the construction of the accommodation camp, reaching a total active capacity of 320 people.
As of the end of June 2025, the project has reached a record 846 days and 6,229,773 person-hours without a lost time incident.