ENKA PW2 project team keeps working hard at the project site. As of the end of 2021, on the West Qurna 1 (WQ1) Produced Water 2 (PW2) Facility Project we are undertaking in Basra, Iraq, the engineering works of which we carried out with our in-house resources, the rates of progress for the procurement work was 86% and 12% for the construction work. A total of 761 working days and 471,676 person-hours have been expended without lost time incident.