SCPX Team is now very close to the total completion of the project as the overall progress reaches 98%. The Compressor Station Georgia -1 (CSG-1) at Gardabani and Pressure Reduction & Metering Station (AREA 81) at Akhaltsikhe have achieved final completions by the end of the 3rd quarter of 2017. Currently, demobilization of temporary facilities is on-going for both AREA 81 and CSG-1 which is targeted to be completed by the end of the1st and 3rd quarters of this year, respectively. Meanwhile, at the Compressor Station Georgia-2 (CSG-2), construction works have reached to 95% completion with the staged handover is on-going in parallel according to schedule. SCPX team targets are to achieve the total completion of the project by June 2018 with the Mechanical Completion and Handover of the CSG-2 facility.