ENKA’s Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Works project in Iraq is progressing at full speed.
As of 9th of February, 2020, the project reached a total completion rate of 77.51%. 3401 precast concrete blocks including U-Shape blocks have been fabricated and 2,590 of these blocks have been installed on their locations.
As of February 4th, 2020, leveling concrete works have commenced on the sections where the preloading activity completed successfully and U-Shape block placement have commenced on February 8th, 2020.
In addition to these, preloading of the first 109 meters of Quay Wall has completed. As of February 9th, 2020, progress of sand filling works have reached a total completion rate of 25.09% and crushed rock placement works have reached a total completion rate of 68.83%.