Kazan 250 MW Combined Cycle Power Plant project, which ENKA is executing in consortium with Siemens in Russia, is progressing apace. As of 17th of August, 2021, while the overall progress of the project including design, procurement and construction activities stands at 23%, the construction progress of project permanent works reached 15%. The project reached 1,291,466 person-hours without lost time incident and a total of 556 employees are working at the project site as of August, 2021.