ENKA’s Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Works project in Iraq is progressing at full speed.
As of 21st of January, 2020, the project reached a total completion rate of 74.5%. All precast concrete blocks apart from u-shape blocks have been fabricated and 2500 of 3177 blocks have been installed on their locations.
Sand filling has commenced behind the quay on 5th of January, 2020 and preloading test which is one of the project milestones was completed successfully for the 1st section of the Quay Wall as of 21st of January, 2020. Additionally, progress of 1-500 kg Crushed Rock placement behind the Quay Wall has reached a total completion rate of %57.