ENKA’s Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Work project in Iraq is progressing at full speed.
As of June 30, 2019, the first block installation of the quay wall was successfully completed.
Overall progress at the project reached up to 41.31%, 1,588 concrete blocks were fabricated and 990,236 person-hours and 370 consecutive days have been achieved without lost time incident.