• 001
  • 002
  • 003

OUED ATHMANIA DAM & WATER TREATMENT PLANT

CLIENT

Ministry of Water Resources – National Agency of Dams

CONTRACTOR

ENKA – Degremont Consortium

SECTOR

Infrastructure

LOCATION

Mila City, Constantine Province, Algeria

SCOPE OF WORK

Engineering, Procurement, Construction

PROJECT DURATION

Dam: August 2002 – April 2007

Water Treatment Plant: December 2004 – September 2007

Project Description

ENKA started the Oued Athmania Dam project in August 2002 and completed in April 2007. The contract included civil engineering works as well as the design, supply, erection, and start-up of the hydraulic, electric and control equipment. The dam reservoir is located at 30 km northwest of the Constantine Province, in the Mila City in East Algeria and was a part of the master project named “Transfer of Beni Haroun”. It aimed to transfer the water collected from Beni Haroun and Bou Siaba towards the six cities of Batna, Kenchela, Mila, Oum El Bouaghi, Constantine and Jijel, where the demand for drinking water and agricultural irrigation water had increased. The dam has a height of 44 m, a length of 630 m, and a reservoir capacity of 33.6 million m3. It has a combined concrete tunnel and 313 m long, derivation gallery. The derivation gallery is able to drain the water with a maximum flow rate of 60 m3/second. The pipeline capacity is 4 m3/second for the drinking water and 2.5 m3/second for the irrigation water.

The Water Treatment Plant project was awarded to ENKA and Degremont (France) consortium in December 2004. ENKA’s scope of construction works included detail design, material supply, civil and structural construction as well as the leakage tests of the structures. The design, supply, erection and start-up of the raw water supply pipeline were also included in ENKA’s scope of work. The early water supply phase of the construction began in February 2005 and was completed by December 2006. The final phase was completed in September 2007 as scheduled. The plant has a capacity of 270 thousand m3 of treated water per day.

Unique Challenges

  • Soil in the region consists of high plasticity clay and under natural conditions it was impossible to use it as a fill material in an earthwork dam according to the specifications. For this reason, special treatment method was developed and used by engineers to use clay in earthwork filling.

ENKA Scope of Services

ENKA’s scope for the Oued Athmania Dam project included civil engineering works as well as the design, supply, erection, and start-up of the hydraulic, electric and control equipment. The major work items are 1 million m3 of excavation, 2.4 million mof filling, 30,000 mof concrete, 40,000 m of drilling and injection.

ENKA’s scope for the Water Treatment Plant project included detail design, material supply, civil and structural construction as well as the leakage tests of the structures. The design, supply, erection and start-up of the raw water supply pipeline were also included in ENKA’s scope of works. Major work items entailed 255,000 m3 of excavation, 205,000 m3 of filling, 10,500 m of jet grouting, 1,000 m of piling, 50,000 mof concrete, 5,500 tons of rebar, 94,000 m2 of formwork and 500 m of raw water pipeline with 1,600 mm diameter steel pipes.

Dam Height (m) x Length (m) 44 x 600
Tunnels Section (mxm) x length(m) 7.5 x 5.5 x 270
Section (mxm) x length(m) 3.25 x 3.25 x 600
Shafts Diameter (m) x Depth (m) Dia2.6 x 25
Caverns Size (mxmxm) 15 x 25 x 12
Depth (m) Length (m) 870
Shaft Linings Depth (m) 25
Steel Liners for Pressure Tunnels Diameter (m) x Length (m) Dia 2.7-2.4-1.6 x 184

Significant Features and Accomplishments

  • Provided much needed water from Beni Haroun and Bou Siaba to the six cities of Batna, Kenchela, Mila, Oum El Bouaghi, Constantine and Jijel, where demand for drinking water and agricultural irrigation water had increased rapidly at the time.

Key Quantities

Dam (Height & Length) 44  x 630
Excavation (Dam) 1 million m3
Filling (Dam) 2 million m³
Concrete (Dam) 30,000 m³
Drilling and injection (Dam) 40,000 m
Excavation (Water Treatment Plant) 255,000 m3
Filling (Water Treatment Plant) 205,000 m3
Jet grouting (Water Treatment Plant) 10,500 m
Piling (Water Treatment Plant) 1,000 m
Concrete (Water Treatment Plant) 50,000 m3
Rebar (Water Treatment Plant) 5,500 tons
Formwork (Water Treatment Plant) 94,000 m2
Raw water pipeline (Water Treatment Plant) 500 m
Steel pipes (Water Treatment Plant) 1,600 mm

Gallery

Related Projects

San Juan Cruise Port Development Project

San Juan Cruise Port Development Project

Current Infrastructure Puerto Rico
Oyu Tolgoi Underground Project

Oyu Tolgoi Underground Project

Current Infrastructure Mongolia
Corridors 8 & 10d Motorway Project

Corridors 8 & 10d Motorway Project

Current Featured Infrastructure North Macedonia