The majority of earthworks and drainage in Sector 1 have been completed, and paving and finishing works are in progress. Piling, foundations, elevations, beam installation and deck construction are advancing rapidly, and the laying of asphalt in the main alignment has started as well.
Excavation, fill, embankment scour protection works and piling, foundation, elevation works for bridges are progressing simultaneously in Sector 2. Precast beam production and installation works are ongoing as well.
In Sector 3, earthworks, embankment scours protection works, piling, foundation and elevation works for bridges are also progressing. Additionally, the Adrani (second) camp with a capacity of 1,000 personnel, has become fully functional in September 2022 to serve employees working in Sectors 2 and 3.
Currently, over 3,800 employees are working on the project. A total of 26.3 million m3 of excavation, 10.6 million m3 of fill, 344,000 m3 of concrete, 175,000 m3 of subbase installation and 66,600 tons of asphalt installation works have been completed.