Currently, over 3,700 employees are diligently working on a wide range of works.
A total of 38.3 million m3 of excavation, 15.2 million m3 of fill, 490 thousand m3 of concreting, 480 thousand m3 of subbase installation and 300 thousand tons of asphalt installation works have been completed.
The project’s target is to add another 11 kilometers to Sector 1 by the end of 2023, extending the length of the opened section to 27.5 kilometers.
In Sector 2 and Sector 3, progress is being made concurrently on earthworks, drainage, and structures, with paving works also commencing in Sector 2.
The Bechtel-ENKA JV has ensured the safety and quality of the project by providing HSE and Quality training to all project personnel, adhering to the requirements of various disciplines.
A total of 7,213,281 person-hours and 217 days had been worked without any lost time incident (LTI) on the project as the end of October 2023.