The major achievements of 2024 included the commencement of the Ball Mill, one of the most critical pieces of equipment of the project, the successful completion of the July 2024 Plantwide Shutdown works, and the handover of critical water and floatation systems, which will enable increased production. Additionally, the project successfully completed 193 piping and 86 electrical tie-in connections to the existing plant units during the local isolation and plant-wide shutdowns since the beginning of the project. The project is planned to be fully completed by mid-2025 with the finalization of the Grinding Building works.
For recognition of Excellence of Business “BEST of BEST”, ENKA was awarded the Oyu Tolgoi Project CRM (Critical Risk Management) Contractor of the Year 2024 by the client. We extend our heartfelt gratitude and congratulations to our project team.