ENKA’s project of Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Works in Iraq is progressing at full speed. As of April 23 2019, the process of screening approximately 1,200,000 m3 sea bottom was completed.
The rate of overall completion on the project reached 35.54% with 1,147 concrete blocks produced, 752,294 person-hours and 303 days worked without lost time incident (LTI).