ENKA’s project of Umm Qasr Basra Multi-purpose Terminal, Container Terminal Yard 5, Quay Wall & Marine Works in Iraq is progressing at full speed.
As of 28th of June, 2020, construction progress at the project reached up to 97.44%. The progress of in-situ concrete pouring along quay wall has reached up to 91,62%. The progress of filling works of sand and 1-500kg crushed rock behind quay wall have reached up to 87,98% and 99,42%, respectively. Also, out of 46 pcs bollards and fenders which will be placed in total; respectively, 28 pcs and 19 pcs have been installed on their locations.
As of 28th of June, 2020, installation of 3452 pcs precast block which is one of critical activities of the project has been completed.
Furthermore, handover inspections have also commenced.